Is it possible to open a project (of about 10 tasks), start it on the first task and have BestSync automatically start the next task on the completion of the first ...WITHOUT creating a schedule?
I only one one task to run at a time.
Thanks for any help.
Don
Automatically start next task without schedule
Re: Automatically start next task without schedule
You can use the "Application" setting to run multiple tasks after the task is synchronized.
Please refer to the attached grphics.
Please refer to the attached grphics.
- Attachments
-
- Start Next Task After Sync
- StartNextTask.png (39.52 KiB) Viewed 4797 times
-
- Task ID
- TaskID.png (45.31 KiB) Viewed 4797 times
Re: Automatically start next task without schedule
OUTSTANDING! You guys are the BEST!
Don