task gets cancelled when unable to connect sftp server occurs

Welcome to BestSync Support Forum!
If you have any questions, comments, concerns, suggestion, please summit here, we'll try to reply you in short time.
Thank you!
Post Reply
gracelim
Posts: 68
Joined: Fri Mar 17, 2017 4:18 am

task gets cancelled when unable to connect sftp server occurs

Post by gracelim »

hi,

i notice task (real sync or scheduled) gets cancelled when bestsync is unable to connect sftp server for x tries and we need to manually start it again.

is there a way for bestsync not to cancel the tasks as no one is manning it 24x7 ?

bestsync version 14.0.1.6

Grace
RiseFly
Site Admin
Posts: 1111
Joined: Tue Nov 03, 2009 2:51 pm

Re: task gets cancelled when unable to connect sftp server occurs

Post by RiseFly »

You can just set a short schedule to start the start the task in a short period automatically.
gracelim
Posts: 68
Joined: Fri Mar 17, 2017 4:18 am

Re: task gets cancelled when unable to connect sftp server occurs

Post by gracelim »

i do not understand what do you mean? how shall i do that using bestsync?
RiseFly
Site Admin
Posts: 1111
Joined: Tue Nov 03, 2009 2:51 pm

Re: task gets cancelled when unable to connect sftp server occurs

Post by RiseFly »

You can set a larger retry times in "Copy Options" tab, so that the task tries more times when the connection error happens.
Or you can set a "Minutely" schedule in "Schedule" tab, so that the task is started in the short period.
gracelim
Posts: 68
Joined: Fri Mar 17, 2017 4:18 am

Re: task gets cancelled when unable to connect sftp server occurs

Post by gracelim »

i also have a task that is scheduled 1 min . but it got cancelled once bestsync detects unable to connect sftp server after x tries.
we have to manually start it.
RiseFly
Site Admin
Posts: 1111
Joined: Tue Nov 03, 2009 2:51 pm

Re: task gets cancelled when unable to connect sftp server occurs

Post by RiseFly »

You can not expect BestSync doing synchronization if it can not connect to the server.
A shorter schedule is the best selection.
gracelim
Posts: 68
Joined: Fri Mar 17, 2017 4:18 am

Re: task gets cancelled when unable to connect sftp server occurs

Post by gracelim »

what i expect is for it not permanently stop the task and have to manually start the task again.

this means i could not use real time synchronization as it stops the task permanently once it is unable to do synchronization after x tries.

i have increase the retries from 3 to 10, and the task gets permanently cancelled.
Post Reply